|
| |
| |
|
SM&F wins prestigious design award in competitive New York market (Continued)

Project Team: Architect: Dario Designs, Inc.
Engineers: Daniel W. Speight, P.E., Structural William F. Hoelter, P.E., Mechanical Daniel P. Grant, P.E., Electrical
General Contractor: Turner Construction
Project Overview:
“Times they are a changin’.”
Businesses are going leaner and meaner
and The New York Times newspaper company
is no exception. According to CBS News,
The Times said research has found that
readers, particularly younger people
and communities, prefer a newspaper
that is 1 ˝” smaller in width than their
current print size. The New York Times
Company purchased a new press and packaging
equipment to accommodate this change.
The addition of this new production
equipment required our team to design
significant additions and renovations
to the existing Queens, New York facility
that started production during the second
quarter of 2008. The Times decided to
consolidate their New York-area production
and improve their College Point facility
avoiding approximately $50 million in
capital improvements at the New Jersey
facility. When all was said and done,
it cost approximately $150 million to
consolidate operations and reduce the
newspaper’s width. Our team designed
a 50,000 sf packaging addition; a 10,000
sf laydown addition/renovation which
included relocating the existing entrance
lobby and credit union; renovation of
the plate making area; miscellaneous
renovations to the lockers and production
support area; and modifications to the
site to accommodate 50 new parking spaces,
50 new fleet driver parking spaces,
new fleet parking, and the parking areas
displaced by the packaging addition.
Structural Systems:
The addition is a two-story
steel structure. The lateral load resisting
system is steel moment frames containing
beams as large as W40x167 and columns
as large as W14x257. The structure is
founded on concrete pile caps and grade
beams which are supported by 14 inch
diameter by 110 foot long concrete-filled
steel pipe piles. The ground floor is
a two-way concrete slab and the second
floor consists of steel composite beams.
Structural Challenges and Solutions
Developed:
The structural team encountered numerous
challenges during the design phase.
New piles had to be setback from the
existing structure to allow adequate
rig clearance. As a result, cantilevered
grade beams were utilized to accomplish
this task. The presence of highly compressible
soils significantly impacted foundation
and underslab utility design. The Geotechnical
Engineer estimated up to five feet of
settlement due to the three and a half
feet of fill that had to be added to
the site. As a result, various utility
vaults and pits were designed to prevent
damage to the underslab utilities. This
was accomplished by hanging concrete
pits and trenches from the structural
ground floor slab. An exterior utility
vault also was designed and located
immediately adjacent to the pile-supported
structure. This concrete utility vault
will house the fire line, which was
jointed in two locations to prevent
damage during the anticipated five feet
of settlement. The vault end walls will
be infilled with wood studs and Styrofoam
immediately above and below the fire
line to allow for vertical movement
(due to the settlement).
| |
| | |
|
|